DECA Project Management Events: Format and Requirements

By The DecaLive team

Project Management events: run a real project, write a 20-page report and present in 15 minutes. Six events, the required outline and scoring for 2026-27.

Share
Events

DECA Project Management Events: Format and Requirements

DECA's Project Management events ask you to run a real project from start to finish, write it up in a report of no more than 20 numbered pages, and present it to a judge in a maximum of 15 minutes. The event is scored out of 200 points: 100 for the written entry and 100 for the presentation. An entry is one to three chapter members, and every member must present.

Season: 2026-27. Last verified October 8, 2026 against the DECA Guide 2026-27 and deca.org. Read the current guidelines and Penalty Point Checklist yourself before you submit. DecaLive is not affiliated with DECA Inc.

The six Project Management events

All six are in the Business Management and Administration cluster, and DECA says the guidelines are exactly the same for each. Each category is still judged as its own event, and a project can only be submitted in one of them.

  • Business Solutions Project (PMBS): work with a local business or organization to identify a specific operations problem and implement a solution.
  • Career Development Project (PMCD): promote or educate people on the knowledge and skills needed for careers, such as through career fairs, mock interviews or resume workshops.
  • Community Awareness Project (PMCA): raise awareness of a community issue or cause.
  • Community Giving Project (PMCG): raise funds or collect donations for a cause or charity.
  • Financial Literacy Project (PMFL): promote financial literacy, for example through seminars or workshops for students.
  • Sales Project (PMSP): raise funds for your local DECA chapter.

Pick the category by what the project is for, not by what sounds easiest. A fundraiser for a charity is Community Giving. The same fundraiser for your chapter is a Sales Project.

What the event expects you to do

According to the guide, participants identify a problem, develop a project management plan for it, implement the project using project management skills, and then write a report and presentation about it. Because the project has to actually happen, the timing matters: it can begin any time after your association's previous conference and runs until the start of the next one. Starting early in the school year leaves time to execute, measure results and write honestly about what went wrong.

Required written outline

The guide says the outline must be followed and every section must be titled, including the bibliography and appendix. The body starts with the Executive Summary as page 1.

  1. Executive Summary: a one to three page description of the project.
  2. Initiating: the statement of the need or opportunity, and the project scope (purpose, rationale and expected benefits).
  3. Planning and Organizing: project goals; a human resource plan (roles, skills, responsibilities); a schedule with 2-4 major milestones and a timeline for each; a quality management plan with key metrics; a risk management plan (potential issues, impact and response); and a project budget that includes monetary and in-kind donations where they apply.
  4. Execution: a description and documentation of how the plan was carried out.
  5. Monitoring and Controlling: how you monitored schedule, budget and quality, and the issues you hit and how you handled them.
  6. Closing the Project: evaluation of your key metrics, lessons learned for each project management process, and recommendations for future projects.
  7. Bibliography (required).
  8. Appendix (optional): exhibits such as questionnaires, letters or meeting minutes.

Page limits: what counts

  • Counts: everything from the Executive Summary through the bibliography and appendix, up to 20 numbered pages in total.
  • Does not count: the title page and the table of contents, which are unnumbered. The table of contents can be single-spaced and run more than a page.
  • Does not count: the signed Prepared Event Statement of Assurances and Academic Integrity. Submit it with the entry and leave it out of the numbering.
  • The title page must name the event, your school and address, participant names and the date.

How the written entry is scored (100 points)

The Written Entry Evaluation Form scores seven items in four bands: Novice, Developing, Proficient and Exemplary. These are the top scores per item on the 2026-27 form.

  • Executive summary: 10
  • Initiating: 10
  • Planning and organizing: 20
  • Execution: 20
  • Monitoring and controlling: 10
  • Closing the project: 20
  • Professional standards (layout, business language, grammar): 10

Planning, execution and closing are worth 60 of the 100 points. The form rewards interconnected plan components, documentation of how the plan was carried out, and reflection that uses your key metrics. A report that describes a good idea but gives little evidence of what actually happened leaves points on the table.

The 15-minute presentation (100 points)

You present as the project managers. The presentation form gives up to 15 points each for initiating, planning and organizing, execution, monitoring and controlling, and closing the project (75 total), plus up to 5 points each for organization, effectiveness, delivery, presentation design and overall impression (25 total).

  • The 15 minutes include the judge's questions. DECA does not set how long you speak, so decide your split and rehearse it.
  • Every participant must take part.
  • Each participant may bring a copy of the written entry or note cards to use as reference.
  • Visual aids must be easy to hand carry, and participants set them up themselves. No wheeled carts, no power or internet is supplied, no food or drinks, and set-up time counts against your 15 minutes.
  • Flyers, brochures and business cards may be left with the judge. Items of monetary value may be handed over but not left.

A practical sequence for the season

  1. Download the guidelines, the Written Entry Evaluation Form and the Penalty Point Checklist from your event page before you start.
  2. Choose a category, then write the need and scope in a few sentences. If you cannot, the project is not ready.
  3. Set 2-4 milestones, assign roles, and decide what you will measure before you begin executing.
  4. Keep records as you go: dates, costs, issues and fixes. The execution and monitoring sections depend on them.
  5. Draft the report in the required order, then cut to 20 pages and check numbering and section titles.
  6. Practice the presentation with timed questions so each teammate can answer about any section.

What we could not confirm

We did not verify your association's entry deadline, the ICDC upload window or the details of the penalty point rules, which you should read on the checklist itself. The event page we checked did not state a points total or a prep time, and some of its linked resources were placeholders. Our written events overview and submission deadline posts cover what is known about dates.

Frequently asked questions

The answers below match the official pages and guide linked at the end of this post.

When your draft is ready, DecaLive can give feedback against the rubric and point to your top fixes. Scores are estimates, not official DECA scores. Learn more on the about page, or browse the events in the app.

How helpful was this article?

Frequently asked questions

How long can a Project Management entry be?
The body is limited to 20 numbered pages, including the bibliography and the appendix if you attach one. The title page, the table of contents and the signed Statement of Assurances and Academic Integrity are not counted.
How long is the presentation?
A maximum of 15 minutes, including time for the judge's questions. Visual aid set-up time counts toward the 15 minutes.
How many points is the event worth?
200 points before penalties: 100 for the written entry and 100 for the presentation.
When can the project start?
The guide says a project may begin any time after your association's previous conference closes and run until the start of your next association conference.
Can I enter the same project in two categories?
No. DECA says a project can only be submitted in one event category.
Can I reuse last year's project?
DECA says repeating a chapter's strategy is fine if it serves the chapter, but teams are challenged to do more than update last year's written project. Plagiarizing a project judged previously automatically disqualifies the entry.

Official sources 路 last verified

Dates and rules change. Confirm with DECA or your state association before you plan around them.

More from the blog

  • Events

    DECA Written Events: Which Events Require a Paper (2026-27)

    The DecaLive team

    DECA Written Events: Which Events Require a Paper (2026-27)

    DECA's prepared events require a written project plus a presentation. Here are the high school event families, team sizes and how to choose in 2026-27.

  • Interview prep

    Preparing for the judge interview about your own entry

    The DecaLive team

    Preparing for the judge interview about your own entry

    Judges ask about your research, your numbers and your weakest sections. Here is how to prepare for questions only you can answer.